In order to ensure that we do not ship broken things we need to test all changes before releasing them.

Requirements

  • Guarantee stability by testing the entire system before releasing it

  • Support new Kubernetes versions quickly after their release

  • Release new features and fixes in a regular and fast way

  • Be able to hotfix old stable releases (this does not mean that we support every old release forever)

  • Be able to fix critical bugs/security issues within a few hours while not sacrificing stability

Versioning Overview

Yaook/k8s is developed and versioned according to cycles. Each development cycle has a predefined amount of to-be-implemented features (but can of course have additional features and fixes implemented). During each cycle contributors can merge changes to the main branch (devel) of the k8s repository.

When the cycle ends all changes on the main branch are pushed to a release-prepare/v$Major.$Minor.$Patch branch. The goal of the release-prepare/v$Major.$Minor.$Patch branch is to have a chance to test changes in a stable and controlled way. Ideally no changes are made to the release-prepare/v$Major.$Minor.$Patch branch anymore. Only necessary hotfixes are allowed.

The release-prepare/v$Major.$Minor.$Patch branch is kept like that for a week at which point it merges to (or creates) a (new) release-branch release/v$Major.$Minor and gets a final version number.

Detailed branching model

The repository is structured in four branch-types:

devel

The main working branch of the repository. Any change is first merged in here. Code in here can be expected to pass all linting as well as very basic functionality tests. When developing on Yaook/k8s this should be your base branch. You should not run any useful deployment from here. This branch is the only long-living branch.

feature

All changes are developed in feature or fix-branches (the name is free), branching off and merging back to devel and therefore passing the beforementioned tests.

release-prepare/v$Major.$Minor.$Patch

For every major and minor release we have a release-branch. This version should already be stable enough that it is usable for non-prod use cases.

release/v$Major.$Minor

For every major and minor release we have a separate branch. The release-prepare/v$Major.$Minor-branch is merged into or generates a new branch.

branching-model

Versioning specification

We define the following versioning scheme following the SemVer concept (https://semver.org/) $Major.$Minor.$Patch:

  • We increment Major by 1 if we have an incompatible change.

  • We increment Minor by 1 every time we added at least one new feature in the release. It starts from 0 for each major release.

  • We increment Patch by 1 for every release not introducing a new feature. It starts from 0 for each normal release.

Yaook/k8s implementation

The following describes the practical implementation of these concepts.

The release pipeline of the Yaook/k8s repository is following these steps:
  • create a release-prepare/v$Major.$Minor.$Patch-branch based off
    • devel, if it’s a major or minor release

    • the corresponding release/v$Major.$Minor-branch, if it’s a patch-release
      • merge devel into it

  • on the branch do the following:
    • calculate the next version number based on the provided releasenote-files since the last release and write it to the version-file

    • generate the changelog using towncrier and remove the old releasenote-files

The pipeline for the release-prepare/v$Major.$Minor.$Patch-branch does the following:
  • run all tests (linting (depending on changes), cluster-tests, diagnostics)

  • tag the commit with v$Major.$Minor.$Patch-rc-<build-nr> if it’s a major or minor release

  • create a delayed job (one week) which
    • merges to (or creates the new branch) release/v$Major.$Minor

    • triggers a MR back to devel

The pipeline for release/v$Major.$Minor-branches
  • does again some basic linting (depending on changes),

  • generates and publishes the documentation,

  • tags the release with v$Major.$Minor.$Patch and

  • creates a Gitlab Release.

Hotfix process

Please read the full section before starting a hotfix-process. We will outline the mandatory steps here.

Why we established this process

We might from time to time need to build hotfixes for yaook/k8s. In this case we need to make sure each release has

  • the correct version number,

  • a changelog entry,

  • a tag and

  • a gitlab-release

Also we have to make sure the version and the changelog of devel is in sync with the latest release.

We introduced a pipeline which will be triggered, if we have a MR with a hotfix/..-branch as source which will take care of the version and the changelog. The pipeline for the release/v..-branch will take care of tagging and gitlab-releases, but older releases may not have those jobs integrated, for manual intervention see here.

The procedure

Attention

See below for the case there is an open release-prepare/v$Major.$Minor.$Patch-branch around!

The following steps are mandatory for the hotfixing-process, the details are up to you and the special case, but we also added a detailed guideline in our coding guide:

  1. For every release needing the hotfix, create a branch hotfix/v$Major.$Minor/$name off of release/v$Major.$Minor

  2. Somehow commit the fix to the branch and create a MR against release/v$Major.$Minor.

We will update the version-number in version accordingly and create the changelog using towncrier. Please make sure the version number is correct (it’s a fix for the corresponding release) before merging.

Important

Place your releasenote inside docs/_releasenotes/hotfix.

If you have to update the latest release, make sure you also update version and the changelog on devel accordingly as those should always be in sync with the latest release. Either by also introducing the fix to devel via the hotfix/$latest-release/$name branch or by just commiting the needed updates.

This process ensures that each hotfix has run through the normal validation pipeline and we can consider it stable.

Important

Make sure the changes on devel and the latest release are identical (esp. the MR-IID in the changelog) as this otherwise could lead to conflicts on the next patch-release.

Manual intervention for older releases

Important

For releases older than this change (February 2024) you need to do the version and changelog-change manually. To do so, do:

  1. Change the line in version from x.y.z to x.y.z+1.

  2. Add the change in the changelog directly.

For older releases it may be the case the ci-pipeline does not everything which is included now. Make sure the following is done in the release/v$Major.$Minor-branch (if not, do it manually)

  1. Create a tag.

  2. Create a gitlab-release from the tag.

Special case: There is an open release-prepare-branch around

Warning

This process is a proposal and has not been tested yet.

If there is an open release-prepare/v$Major.$Minor.$Patch-branch, this means that we are in the process of rolling out a new release and haven’t finished the process yet. Please have a look at its pipeline. We will differentiate two cases:

  1. The merge-to-release-branch job hasn’t started yet.
    1. Stop the pipeline.

    2. Add the fix as a new commit somehow into the release-prepare/v$Major.$Minor.$Patch-branch and start the pipeline for the branch again (this should happen automatically).

    3. For all older versions needing the hotfix proceed like described above. (Have in mind that the release-prepare/v$Major.$Minor.$Patch-branch could also be a fix-release and merge to the last release/v$Major.$Minor-branch)

Important

Don’t create a hotfix/devel/$name branch merging back to devel as the hotfix will be merged via the release-prepare/v$Major.$Minor.$Patch-branch!

hotfixing-strategy-for-open-release-prepare-branch
  1. The merge-to-release-branch job has been triggered, but the MR back to devel or the release-branch isn’t finished.
    • Please wait for the release to be fully finished. Afterwards follow the process described above.

Release withdrawal process

Please read the full section before starting the release-withdrawal-process. We will outline the mandatory steps here.

In this chapter we will call the release to be withdrawn simply “the release” and its successors of the same kind (minor, patch) “the successors”.

Why we established this process

We might need to withdraw a release for the following reasons:

The procedure

Tip

We will utilize the hotfixing-process for withdrawing releases. Make sure to understand it before proceeding.

Withdrawing a release basically means to:

  1. Mark the release as withdrawn in our changelog

    We do this by appending [withdrawn] to the headline of the release AND its successors. Additionally the reason for the withdrawal shall be inserted as a notice below the headline of the release.

    Our Gitlab releases page will be updated in the same manner.

  2. Revert the offending changes introduced by the release OR fix them right away

    For reversal the tools of our source control management are to be used. Attention shall be given to changes introduced by successors which depend on the to be reverted ones.

  3. Publish a new “replacement” release

    We are using hotfixing-process to publish the changed changelog and the reverted changes/fixes together in a single new release (that contains no other changes).

    The new release must be a patch release which acts as a replacement for the withdrawn release(s) and an update target for users of prior releases.

    If the reverted changes or fixes are not suitable for a patch release (example 1), we additionally create a “replacement” minor/major release as an update target for users of the withdrawn release(s) and clearly state in the “replacement” patch release that users of the withdrawn release(s) must update to the “replacement” minor/major release instead.

    In case the next minor/major release series already started, we instead hotfix it as well (example 3).

    Exception: When fixing a SemVer violation we just add the release note of the reverted change(s) to the release notes of the next minor/major release effectively moving the change to the next suitable release. (example 2)

Examples
    1. Patch release contains breaking change

    ...
    5.1.0
    5.1.1
    5.1.2 [withdrawn]  <-- includes breaking change
    5.1.3 [withdrawn]
    5.1.4 [withdrawn]
    ---
    5.1.5              <-- patch release withdraws 5.1.2-5.1.4 + reverts breaking change
                           (target for users of releases up to 5.1.1)
    6.0.0              <-- next major release re-adds breaking change
                           (target for users of releases 5.1.2-5.1.4)
    
  • (2) Patch release contains functionality change and next minor release already exists

    ...
    5.1.0
    5.1.1
    5.1.2 [withdrawn]  <-- changes old functionality
    5.2.0
    5.2.1
    ---
    5.1.3              <-- patch release withdraws 5.1.2 + reverts functionality change
                           (v5.1-target for users of releases up to 5.1.1)
    5.2.2              <-- patch release in next minor release series
                            adds functionality change to release notes of 5.2.0
                           (v5.2-target for users of all releases)
    
    1. Release contains security vulnerability

    ...
    3.0.0
    3.0.1
    3.1.0 [withdrawn]  <-- introduces severe security vulnerability
    4.0.0
    ---
    3.1.1              <-- patch release withdraws 3.1.0 + adds security patch
                           (target for users of releases up to 3.1.0)
    4.0.1              <-- patch release hotfixes next release series in the same manner